Unveiling the Continuing Saga: The Northvolt Battery Factory in Heide, Germany
- By Kilian Schroeder**
- + - 2 Min
Government's High-Profile Project Under Scrutiny by Financial Audit Authority under Traffic Light Administration - Audit of Ampel Administration's Showcase Endeavor Conducted by Federal Auditing Authority
Amid the waves of the Swedish battery cell manufacturer Northvolt's financial turmoil, the Federal Audit Office has stepped into the fray. As confirmed on request, the authority has been scrutinizing the federal and state of Schleswig-Holstein's funding for the construction of a battery factory in Heide since the beginning of the year [Enrichment Data: 1]. The Federal Audit Office, discretion being its key, has remained tight-lipped about the specifics and duration of the audit.
The federal government and the state of Schleswig-Holstein had committed over a billion Euros to support the construction of a battery cell factory in Heide [Enrichment Data: 1]. After prolonged negotiations over public funding, the KfW Bank extended a 600 million Euro convertible bond, with both the federal government and Schleswig-Holstein each offering half the guarantee. In addition, a total of 700 million Euros in subsidies was earmarked [Enrichment Data: 1]. Northvolt aimed to invest between 4 and 5 billion Euros in the Heide location.
Crumbling Foundations: Northvolt's Collapse in Sweden
Shortly following the official site selection in early 2024, whispers of trouble at Northvolt's first "gigafactory" in Skellefteå, northern Sweden, began to circulate. Production of batteries fell short of expectations, BMW scrapped a billion-dollar order in June 2024, and the company's debts mounted significantly [Enrichment Data: 2]. In November 2024, Northvolt filed for bankruptcy protection in the US, and negotiations for a lifeline failed. The company eventually filed for insolvency in its native Sweden in March of this year [Enrichment Data: 2].
The future of the Heide site and the German taxpayers' investment remains uncertain. Until recently, the Federal Ministry of Economics maintained that German subsidiaries of Northvolt were financially autonomous and thus exempt from the insolvency proceedings. Yet, even the German subsidiary Northvolt Germany TopCo GmbH has now sought a restructuring procedure, according to "Der Spiegel's" recent report [Enrichment Data: 3].
Steady as She Goes: The Northvolt Drei Project GmbH Presses On
A representative of the German "Northvolt Drei Project GmbH," responsible for the project's progress in Heide, stated that none of the German companies were implicated in the Swedish insolvency proceedings. They expressed optimism about the Heide location, asserting that the "Project GmbH" itself was unaffected by insolvency [Enrichment Data: 3].
However, it remains ambiguous when the previous federal government became aware of Northvolt's predicament. The traffic light government had entrusted PwC with assessing the default risk for the 600 million Euro convertible bond. Despite the production at Northvolt still being far from ready for mass production, the risk was apparently deemed minimal [Enrichment Data: 4]. Former Economy Minister Robert Habeck (Greens) divulged that he became privy to Northvolt's struggles only after contracts had already been agreed upon [Enrichment Data: 4].
The auto industry, too, had indulged high hopes in Northvolt. Volkswagen was the principal shareholder, while BMW possessed a modest stake. Volkswagen is believed to have written off its investment prematurely last year. In the Swedish insolvency proceedings, Northvolt's workforce has been drastically pared, and the quest for purchasers for the various company components continues [Enrichment Data: 4].
Capital is a partner brand of stern. Selected content can be viewed with your stern subscription. More from Capital can be found at www.stern.de/capital.
- Northvolt
- Federal Court of Auditors
- Battery
- Robert Habeck
[1] Enrichment Data: The construction of the battery factory in Heide, Germany, is continuing. The entity responsible for this project, separate from the part of Northvolt's German division that applied for restructuring, remains operational [Enrichment Data: 3]. The project was greenlit in January 2024 with €902 million in funding from the European Commission under the Important Projects of Common European Interest (IPCEI) initiative [1]. The factory is expected to produce battery cells with a capacity of about 60 GWh per year, sufficient to power up to one million electric cars annually [5].
[2] Enrichment Data: The ongoing construction of the Heide factory suggests that federal and state funding commitments are still in place. However, the German Federal Audit Office is investigating the financial crisis at Northvolt, which may impact future funding decisions or management of existing grants [5]. The bankruptcy of Northvolt highlights the risks associated with large-scale industrial projects and the challenges in securing stable funding and investment commitments in the battery production sector [2][3].
[3] Enrichment Data: There is hope that new investors might be found to support the Heide project, as indicated by former Economy Minister Robert Habeck [3]. However, the overall financial difficulties faced by Northvolt and the broader challenges in the European battery production sector could complicate future funding and project stability [2][3]. The fate of the €902 million funding from the European Commission and €700 million in subsidies largely depends on the outcome of the German Federal Audit Office's investigation and the potential involvement of new investors.
[4] Enrichment Data: The Federal Ministry of Economics' claims that the German subsidiaries of Northvolt were independently financed and thus not part of the insolvency proceedings came under scrutiny when Northvolt Germany TopCo GmbH applied for restructuring. It remains unclear whether the German government will reconsider its support for the Heide project in light of these developments.
[5] Enrichment Data: The future impact of the Northvolt crisis on the broader European battery production landscape and related funding initiatives like the Important Projects of Common European Interest (IPCEI) would depend on the success of new investments, the resolution of ongoing investigations, and the stability of the sector as a whole. Governments, industry players, and original equipment manufacturers (OEMs) would need to carefully evaluate potential risks and consider adopting measures to mitigate them.
- The European Parliament, the Council, and the Commission are closely monitoring the ongoing investigation by the Federal Court of Auditors into the federal and state funding for the Northvolt battery factory in Heide, Germany.
- The battery industry, finance, and investing communities are watching the situation carefully, as the Northvolt crisis may have implications for future large-scale industrial projects and investment commitments in the battery production sector.
- The general news, politics, and business world are following the Northvolt heating saga in Germany with interest, as the fate of the €902 million funding from the European Commission and €700 million in subsidies, as well as the overall stability of the European battery production sector, may be affected by the outcome of the German Federal Audit Office's investigation and potential involvement of new investors.